Texas's data center buildout, in reactors
On November 14, 2025, Google announced a $40 billion commitment to build three new Texas data centers (Armstrong + Haskell counties) plus expansions in Ellis County. That announcement now sits inside a much bigger story: ERCOT projects roughly 78 GW of data center demand on the Texas grid by 2030 — close to the entire state's record 2023 peak demand of about 85 GW. Here's what 78 GW of compute load actually translates to in the standard power-source vocabulary.
The 78 GW translation
Hyperscale data centers run as essentially firm load — Dominion Virginia reports an 82% load factor for large data centers, and Duke Energy plans for 80%. Treating ERCOT's ~78 GW projection at an 85% utilization yields roughly 580 TWh/year of new electricity demand — about 14% of all U.S. electricity consumption today.
To supply that with each major power source (using realistic Texas capacity factors):
For scale: Texas already has nuclear. It's not enough.
Texas runs four operating commercial reactors — two units at Comanche Peak (north of Fort Worth, Vistra-operated, 2.4 GW combined) and two at South Texas Project (Bay City, 2.7 GW). At fleet-average capacity factor, those four reactors together deliver about 41 TWh/year.
Set against ERCOT's ~580 TWh of projected new data center load, the entire existing Texas nuclear fleet covers roughly 7%. Filling the rest with new AP1000-class reactors would require building about 60 more — a 16× expansion of the state's commercial nuclear capacity.
The land-use side, at Texas scale
Texas has the best onshore renewable resource in the lower-48 — its solar capacity grew 92% between 2024 and 2026 per EIA. But the math on covering 580 TWh/yr with renewables firmed-up to 24/7 reliable power runs into geography fast. About 9,000 utility-scale solar farms at 100 MW apiece would occupy roughly 8,400 square miles — almost exactly the size of the entire Houston metro area (~8,269 sq mi) or the state of New Jersey (~8,729 sq mi).
The same 580 TWh from onshore Texas wind would take roughly 140,000 turbines spread across 22,000 sq mi — an area larger than West Virginia. The 64 AP1000-class reactors that would deliver the same energy occupy under 85 sq mi of total site footprint — about 1% of the solar land use, or 0.4% of the wind land use.
For natural gas (Texas's grid-staple): about 220 600-MW combined-cycle plants, emitting roughly 230 million tons of CO₂ per year — comparable to the annual emissions of every car in California.
The state knows the forecast might be high
The 78 GW figure comes from ERCOT's long-term load forecast submitted to the Public Utility Commission of Texas in 2025. ERCOT also presented a more aggressive scenario showing peak demand quadrupling by 2032 — which the PUCT promptly sent back as inflated. ERCOT's own CEO Pablo Vegas conceded the interconnection queue (over 220 GW total, ~70% data centers) "reflects higher than expected future load growth."
The likely truth sits somewhere between the queue total (clearly speculative — many projects will never break ground) and the official 78 GW projection. Either way, the direction is the same: Texas needs to build enough new firm capacity to match a state-sized data center buildout, and it needs to do it inside the same deregulated ERCOT market that's already showing capacity-price stress.
The named-project pipeline so far
A partial inventory of disclosed Texas data-center commitments since 2024 — well short of the full 78 GW projection but illustrative of the pace:
| Project | Power (GW) | ~AP1000s equiv. |
|---|---|---|
| Stargate Abilene + Shackelford County (OpenAI/Oracle/SoftBank) | ~3.0 | ~3 |
| Google: Armstrong + 2× Haskell + Wilbarger (announced 2025–26) | ~5.0 | ~5 |
| Fermi America (proposed, partly nuclear-powered) | ~11.0 | ~11 |
| Meta El Paso (announced October 2025) | ~0.5 | ~0.5 |
| Subtotal of named projects | ~19.5 | ~20 |
| Remaining unnamed projects to reach ERCOT 78 GW projection | ~58.5 | ~48 |
Capacity figures from company press releases and ERCOT interconnection-queue reporting; AP1000-equivalent assumes 85% data-center utilization vs 93% reactor capacity factor. Several projects (Fermi America in particular) are speculative or early-stage.
What this means for Texas's grid mix
ERCOT's near-term answer to data center demand has been new gas turbines plus continued solar buildout — EIA forecasts 9.6% generation growth in 2026 alone, with most new megawatt-hours coming from solar (which grew 92% between 2024 and 2026) and natural gas. Coal generation is also rising in some grid regions to backfill dispatchable capacity.
Senate Bill 6 (passed June 2025) gave ERCOT the legal authority to curtail data-center load during grid stress events — a recognition that adding 78 GW of firm-baseload-priced demand to a grid built around variable renewables creates reliability risk. SB-6 also redefined large-load interconnection (≥75 MW) and added transmission-cost requirements designed to make data-center developers pay for the grid they need.
Try the math yourself
Use our compare tool to see how 78 GW of demand stacks up against any single power source for any Texas metro:
Sources
- ERCOT — strategic organizational changes; 225+ GW Large Load interconnection queue (December 2025).
- U.S. EIA — "Rapid electricity demand growth in Texas and the mid-Atlantic": ERCOT growth 11% in 2025, 14% in 2026 driven by data centers and crypto.
- Utility Dive — EIA December 2025 STEO: ERCOT solar growing 92% between 2024 and 2026.
- CNBC — "Red-hot Texas is getting so many data center requests that experts see a bubble": 220+ GW interconnection queue, 70%+ data centers.
- Fox 26 Houston — PUCT pushback on ERCOT's "quadrupled by 2032" forecast as inflated; CEO Vegas statement.
- Office of the Texas Governor and Bisnow — Google's $40B Texas data-center commitment + 6.2 GW PPAs (November 14, 2025).
- Texas Scorecard — ERCOT 77,965 MW data-center demand projection for 2030, up from 29,614 MW in 2024 forecast.
- Data Center Dynamics — Vistra Comanche Peak 2.4 GW; Texas data center coverage.
- arXiv 2509.07218 — Texas Senate Bill 6 (2025): redefined large-load interconnection for ERCOT.
- Existing Texas nuclear capacity: NRC operating-reactor data for Comanche Peak Units 1–2 and South Texas Project Units 1–2.
- Capacity factor and firm-equivalent assumptions: NREL Standard Scenarios 2024; NREL NSRDB regional averages for Texas. See full methodology for assumption details.